Precautions for Chiller Installation
Release Date:
2012-12-02
| Schematic Diagram of External Piping for the Water System ◆ Pay attention to the inlet and outlet positions of the chilled water and cooling water to prevent connection errors. ◆ Install manual or automatic air vents at all the highest points of the water circulation system; ◆ Install thermometers and pressure gauges at the chilled water and cooling water inlets and outlets for easy monitoring. ◆ Install shut-off valves on the chilled water and cooling water inlet and outlet pipelines of the unit to facilitate maintenance. ◆ Install a water filter upstream of the pump suction inlet to prevent impurities from entering the pump and the heat exchanger. ◆ Bypass valves are installed on the chilled water and cooling water inlet and outlet pipelines to facilitate flow rate adjustment during seasonal transitions. ◆ Flexible connectors shall be installed on the chilled water and cooling water inlet and outlet pipelines of the unit. ◆ After completing the inspection of the chilled water piping, apply the insulation layer. |
|
|
Installation Precautions 1. Unboxing and Inspection: Upon arrival at the customer’s site, carefully verify that all items are present and that their quantities and specifications match the packing list. Inspect the equipment and its accessories for any damage; if damage is found, notify the carrier and submit a written claim for compensation. Crown Products shall not be liable for any damage occurring after the equipment has been accepted upon delivery. 2. Lifting and Installation: It is recommended to use a lifting method. When hoisting the unit, ensure that the sling or lifting strap is securely fastened to the designated lifting holes. During lifting, take care to protect the control cabinet and other components from damage. For units weighing 100 kg or more, if on-site lifting conditions are unavailable, the rolling‑and‑translating method may be employed: place four steel pipes beneath sleepers or channel sections to facilitate rolling and translation, ensuring that three pipes remain in contact at all times, with one pipe reserved for replacement. This method is suitable for sites with relatively level ground and slopes of less than 15°. If the unit is equipped with casters, it can simply be pushed into position. 3. Installation Environment: The unit should be installed indoors; if installed outdoors, a rain shelter must be provided. Ambient relative humidity shall not exceed 90%, and the installation site must be free of corrosive substances and gases that could degrade insulation. The installation surface must be level and sufficiently strong; if these requirements are not met, a precast concrete foundation is required. When mounting the unit on a floor, the floor must have adequate strength and stiffness to support the unit’s operating weight. Sufficient clearance for maintenance must be provided around the unit: a 1-meter clearance should be maintained at the front and rear, and 0.6 meters on each side and above. 4. Water System Requirements: When using river water or groundwater, the water must be filtered prior to entering the equipment to remove sediment and contaminants. The water quality must meet industrial‑water standards; otherwise, appropriate water‑treatment measures are required. Refer to the “Industrial Cooling Water Design Code” for relevant treatment procedures. Shut‑off valves must be installed at the equipment’s inlet and outlet to facilitate routine maintenance. An automatic or manual flow‑control valve shall be provided at the cooling‑water inlet to enable flow adjustment during seasonal changes. Flow switches or differential‑pressure switches meeting the specified requirements must be installed at both the inlet and outlet of the water system. A water filter must be installed at the pump suction inlet to prevent impurities from entering the pump and the unit’s vessel. It is recommended to install thermometers and pressure gauges at the inlet and outlet to support routine maintenance. For installation details of these components and other pertinent considerations, refer to the “Water System Connection Diagram.” 5. Electrical System Requirements: The power distribution capacity must meet the unit’s specifications; voltage fluctuations shall not exceed ±10% of the nameplate voltage, and phase-to-phase voltage imbalance shall be ≤2%. The electrical control cabinet must be adequately ventilated, and no foreign objects or water shall be allowed inside. |
|
|
Precautions for Initial Operation of the Unit 1. Water System: Verify that all water‑system piping connections are correct and that the flow direction is proper; open all water valves and start the water pumps and cooling towers. Flush the water‑system piping to ensure cleanliness, and check that all pipe joints are tightly sealed. Purge air from the system, and confirm that pressure gauges, thermometers, flow switches, and flow‑control valves are functioning normally. Run the system for approximately 10 minutes, then close the make‑up water valve and drain the system through the drain outlet. If the water remains very dirty, after draining, add fresh water, run the system for another 10 minutes, and drain again. Repeat this process until the water system is clean. When starting up, activate the chilled‑water and cooling‑water pumps at least 5 minutes in advance; when shutting down, allow a 5‑minute delay before stopping these pumps. 2. Electrical System: Verify that the available power supply capacity meets the installation requirements to support unit startup and full-load operation, with voltage fluctuations within ±10% of the nameplate voltage and phase-to-phase voltage imbalance not exceeding 2%. Inspect that the specifications of all wiring and protective devices comply with the unit’s operating requirements, and confirm that external interlock control components, such as water flow switches, are properly installed and functioning correctly. 3. Unit Section: Verify that the compressor oil level is normal, confirm that the compressor oil‑temperature heater has been running for 24 hours, open all valves in the refrigeration system, and check that all protective devices are in their default settings and that the parameter setpoints are correct. 4. Protective Devices: The unit is equipped with numerous safety protection devices to ensure safe operation. When any one of these devices activates, the corresponding function will be shut down. Even if the unit can continue to operate, it must be stopped immediately for inspection and troubleshooting to prevent more serious accidents that could result from prolonged operation. |
Previous item
Latest Updates
Zhejiang Loda Refrigeration Technology Co., Ltd.
Phone:0571-88587986 88543696 88543697
Address: Xiayang Village, Xiazhuhu Subdistrict, Deqing County, Huzhou City, Zhejiang Province
Fax: 0571-88526093